Ore Tunnel Improvement Work: Service changes between Hastings and Ore / Ashford International from Saturday 19 October to Sunday 3 November 

See all service disruptions

Engineering work details

Starts 19 Oct 2024 to 03 Nov 2024

Train operators affected

Route(s) affected

Southern services between Hastings and Ashford International via Rye

Description

Major improvement work is taking place in Ore tunnel over 16 days between Hastings and Ashford International. All lines will be closed throughout between Hastings and Rye, and for part of the time between Rye and Ashford International.

Saturday 19 and Sunday 20 October:

Buses will replace trains between:

  • Hastings and Ore

  • Hastings and Rye

  • Rye and Ashford International.

An amended train service will run between Brighton / Eastbourne and Hastings.

Monday 21 to Friday 25 October:

Buses will replace trains between:

  • Hastings and Ore

  • Hastings and Rye

  • Rye and Ashford International (before 07:30 and after 18:30 each day).

Between 07:30 and 18:30 each day, a limited train service will run between Rye and Ashford International.

An amended train service will run between Lewes and Hastings.

Saturday 26 and Sunday 27 October:

Buses will replace trains between:

  • Hastings and Ore

  • Hastings and Rye

  • Rye and Ashford International (before 07:30 and after 18:30)

Between 07:30 and 18:30 a limited train service will run between Rye and Ashford International.

An amended train service will run between Brighton / Eastbourne and Hastings.

Monday 28 October to Saturday 2 November:

Buses will replace trains between:

  • Hastings and Ore

  • Hastings and Rye

  • Rye and Ashford International (before 07:30 and after 18:30 each day).

Between 07:30 and 18:30 each day, a limited train service will run between Rye and Ashford International.

An amended train service will run between Lewes and Hastings.

Sunday 3 November:

Buses will replace trains between:

  • Hastings and Ore

  • Hastings and Ashford International

Trains will run to an amended and reduced timetable between Brighton / Lewes / Eastbourne and Hastings.

Replacement Bus Travel Advice:

You can view the bus timetables here:

Please be advised that replacement vehicles may be busier than usual, and you should allow extra time for your journey.

For helpful advice if you need to travel on a rail replacement service, including accessibility information, please use our travel information pages.

You can find the location of your replacement bus by checking station signs or by searching for your station on our station information pages.

Check before you travel:

You can plan your journey using the National Rail Enquiries Journey Planner

Background Information:

Major improvement work is taking place in the 1,402 yard (1,282 m) long Ore tunnel. The work will improve the drainage, and repair the lining on the inside of the structure to prevent water seeping through. This will include concrete spraying of the lining of the tunnel, soil and rock nailing, repair of the brickwork and replacement of some of the track through the tunnel. More information is available on the Network Rail website.